Deep copying an activity definition
You can duplicate an activity definition in a service plan, including any linked schedules and expected costs.
Procedure
1. Go to Maintenance Planner > Activity definitions.
2. Select the activity definition you want to deep copy.
3. On the action menu, click Deep copy.
4. To copy any linked expected costs, select the relevant options.
5. If required, modify the copy’s data, such as its Description.
6. Click OK.
A comprehensive copy is made of the activity definition. The following elements are included in the deep copy:
◦ The selected expected costs;
◦ Linked schedule (with recurring and non-recurring activities).
If you only want to make a regular copy of the activity definition – excluding the linked schedule or expected costs - select the
Copy option in the action menu instead of the
Deep copy option.