Technical Facility Management : Planned maintenance : Work balancing in the graphical planner : Viewing costs and man-hours in the graphical planner
Viewing costs and man-hours in the graphical planner
You can view an activity's expected man-hours and costs in the graphical planner by:
viewing the tooltip information on expected costs and man-hours, by hovering over an individual activity
displaying labels on the activities with the data of the total costs (including or excluding tax) / man-hours
displaying a bar chart with various cost / man-hour totals at the bottom of your screen
The procedure is about using the last two options.
Procedure
1. After making relevant selections on previous selection levels, go to Maintenance Planner > Definitions & schedules.
2. Click the Graphical planner button and select the relevant period view.
3. In order to display labels on activities and display the bar chart, click the Select label options button in the graphical planner's header .
4. Select one of the options: Total costs excl. VAT, Total costs incl. VAT, Total man-hours (in hours). The graphical planner shows labels on the activities, displaying the rounded cost amounts or, if you selected the Total man-hours option, the number of man-hours.
A bar chart at the bottom of your screen shows the totals of the expected costs (including or excluding tax) or the expected total man-hours, for the selected period. Hover your cursor over the chart to summon tooltips with information on the individual layers of the stacked bars.
5. Use the check boxes in the bar chart's legend to show / hide specific types of expected costs from the totals. The following options are available: Display total additional costs, Display total material costs or Display total man-hour costs.
The totals are displayed as follows for the selected period views:
a. 10 years: totals per year
b. 1 year: totals per month
c. 6 months: totals per month
d. 1 quarter: totals per week
e. 1 month: totals per week
f. 1 week: totals per week
6. To switch the labels and bar chart off, click Select label options > No details.