Selecting future activities in the graphical planner
You can select an activity and all its future occurrences in the graphical planner.
Procedure
1. Go to Maintenance Planner.
2. Make relevant selections on the various preceding levels and then go to Definitions & schedules.
3. Click the Graphical planner button.
4. In the graphical planner, select the activity whose future activities you want to select.
5. Right-click and from the context menu select Select future activities or press CTRL + SHIFT.
The activity and all its future occurrences are selected. You can now apply options from the context menu, such as (de)activating or outlining.
See Moving multiple activities in the graphical planner for information about moving a sequence of activities on the planner.